PROJECT NAME NEO CITY WAGHOLI PUNE PRISTINE MAPLE AND JALAN GROUPS ARE ONLY CHEAT CONSUMERS MY FLAT IN PHASE 2 E BUILDING I AWARE ALL THE NEW CONSUMER PLEASE DO NOT BOOK FLAT IN NEO CITY WAGHOLI PROJECT BECAUSE AT THIS TIME NOT ONLY POSSESION DELAYED BUT ALSO SOME REGISTRATION ISSUE.THESE BUILDER ARE ONLY CHEAT CUSTOMER I HAVE BOOK FLAT ON DECEMBER 2011 AND THE POSSESION DATE IS DECEMBER 2013 BUT AT THIS TIME POSSESSION IS PENDING AND WHEN I CALL TO BUILDER OFFICE HE SAYS ONLY NEW DATES.EVERY 6 MONTHS NEO CITY WORKERS ARE CHANGE BECAUSE THESE BUILDERS ARE GUILTY.


Post your reviews / feedback or experience by clicking on the following submit complaint button.
Frustrated?

4 thoughts on “NEO CITY – DELAYED POSSESSION”

  1. 1.Pristine Properties (www.pristinepune.com) , Maple Shelters (www.mapleshelters.com), JALAN GROUP (www.jalangroup.info) cheating flat buyers. How they do 1) They launch a new project and collect booking amounts from flat buyers. 2) For agreement within one month they collect again 20% amount of total cost. 3) After they initiate a demand letters to buyers in the gap of couple of months till 90% of flat cost. 4) Now once 90 % collected where building structure is only ready they stop all work further and launch a new phase 2, phase 3 etc. 5) They move all their labours to new phase to construct building structure only and to collect money from new phase buyers till 90%. 6) They keep building structures only and not giving possessions on time. Thus they earn money from buyers and here flat owners just keep paying interest on home loans and waits for possesions.
    2.Example – Pristine, Maple and Jalan’s project Neo City Wagholi at Pune, they just constructed building blocks only and no possessions to Phase 1, Phase 2 and Phase 3. All these phases paid 90% amount 2-3 years back and no progress of work further.
    3.Humble request here to new buyers if they are looking flat in Pristine Properties or Maple Shelters or JALAN group all of Pune. If you are getting ready possession flats in their any project please go ahead and book. BUT do NOT BOOK YOUR FLAT IN UNDER CONSTRUCTION OF WORK. Else after 90% of work and once 90% amount collected from you they will keep you in hang position for many years, may be 2 or 3 years without any progress. Neo City possessions are pending from 4+ years for phase 1, phase 2 and phase 3 and no progress yet. Kindly check possession reviews before you book a flat for any project.

    1. Rajendra Darekar

      Yes 100% agree
      Dear Sir,
      I would like to bring your attention to my issues regarding cobstruction progress at Neo City – Wagholi site.
      I have booked flat in Phase – II, E 507 in Jan 2012, While booking, March 2013 was the possession date which was verbally communicated.
      Within 8 months from the booking 85% payment paid.

      I have simple question, When we will get occupancy certificate from authorised governing body and peacefull possessions to my home with all amenities which is listed while selling the flats.

      Who is responsible for my financial losses due to delayed construction?

      Why it is not being communicated with us if progress of work is delayed by some reason?

      I have lost my confidence and hopes.

      Best regards
      Rajendra Darekar

      Engineers……”Behind the next big thing…….”

      sent from my samsung smart phone on idea

      On 27 Feb 2015 11:05, “Rajendra Darekar” wrote:

      Dear Sir/s,

      Mr. Dushyant and Bhushan

      To whom it may concerns:

      Almost 07 months passed after our meeting had with Neo City office, we have not received any confirmation on possession date by email or by post.

      From neo city wagholi office nobody is neither giving satisfying answer on possession date nor giving directors contact and address details.

      For your kind information, 85% payment paid in feb 2013. I am paying pre emi interest and almost paid 6 lakh in pre emi interest only. Who is going to pay this amount? Money are not growing on the trees, its comes from our blood and sweat.

      I am paying flat rent as well pre emi.

      If you are least bothered please respond on flat possession.

      Expecting feedback at the earliest.

      Warm regards

      Rajendra D Darekar

      Neo City

      Phase II, E wing, Flat No – 507

      On 16 July 2014 at 17:28, Rajendra Darekar wrote:

      Dear Dushyant,

      This message is alo to Directors of project.

      Mr. Sachin Agarwal, Mr. Jalan

      I am very much disappointed the way progress of Phase – 2, E – Building. I had photographic evidence about the progress of work.

      1. September 2012, 5th floor brick work has completed and plaster was in progress.

      2. July 2013, almost after 10 months, only plaster work completed.

      3. July 2014, after 12 Months, No progress at All. Situation as it is. Project getting delayed beyond the limit. Offered possation date was 31/03/2014 which is already passed. Nobody bothered to inform to customers about delay and real reason of delays in project.

      According to current situation, Only god knows about possation of flats. All other builders projects were completed which was started after Neo City in spite of LBT reason.( which was external factor for delay to you).
      What could be the external factors that influence such so much delays which beyond our imagination.. Seriously something wrong going inside.

      Due to delayed possation I am facing tremendous financial crunch, Paying 20,000 per month Pre Interest only due to Loan is not disbursed fully. In addition 8,000 rupees paying house rent extra.

      I need 20,000 ruppes/month for late possation charges to recover losses which I am getting due to delayed possation of flat.

      I need immediate reply to the mail otherwise I will be free to take further action.

      Your immediate response highly appreciated.

      Regards

      Rajendra Darekar

      08975123229

      On 3 September 2013 15:16, neo city wrote:

      Dear sir,

      With reference to your mail regarding possession of your flat we would like to insure you that you will get it by June 2014.

      this delay is caused by some external factors like implementation of LBT in Pune city which caused building material traders strike for more than two months. Even when the strike was over it took a fortnight to resume supplies.

      Moreover there was a strike of all poarse aggregate & crush sand suppliers in pune city for more than a month which also contributed in delays.

      However for the best of our customers interest we are still trying to cover up the delays caused by the above factors.

      Regards

      NeoCity

      On Fri, Aug 23, 2013 at 9:10 AM, Rajendra Darekar wrote:

      Dear Sir/Madam,

      Sincere request ….

      To whom it may concern.

      I have booked my flat in Neo City – Phase II, E – Building , flat No 507, I am observing from last six month there is no progress in construction work. Phase -3 which is launched after phase – 2 has much more progress but Phase – 2 has behind the phase -2.

      It seems to that possession will not be offered on given deadline. Almost 80 % payment has been paid and we are paying emi’s without knowing when we will get possession.

      This kind of situation is forcing us to knock the door of consumer forum. Hope concern person will answer on this.

      Thanks and Regards….

      Rajendra Darekar

      +918975123229

      Engineers… “Turning ideas into reality.”

      Engineers … “Behind the next big

  2. Sunil - Advocate

    If as per agreement flat possession date is crossed then builder of Neo City Wagholi Pune i belive here Pristine Properties, Maple Shelters, Jalan group ( [email protected], pristinepune.com, mapleshelters.com, jalangroup.info ) must give compensation to you. This compensation must be equal to month rent and applicable only till you get possession. This is legal under Section 8 of the Maharashtra Ownership Flats Act. If any builder is proved for non compliance under Maharashtra Ownership Flats Act then it’s license can be suspended and for new projects they can be rejected on process approvals.​

    Advocate – Mr Sunil

  3. AGREED WITH ADV SUNIL,DR FRIENDS PL APPOINT ADV SUNIL OR ANY OF YOUR KNOWN LAWYER,MY PROB IS SIMILAR ,HAVE BOOKED FLAT IN MAPLE BUILDERS PROJECT,WHICH THEY LAUNCHED 2 MONTHS BACK,”APLA GHAR”AS PER SCHEME BUYER HAS TO PAY ONLY ONE LAKH AND DO THE REGISTRATION,REST ALL TOTAL AMOUNT AFTER 3 YEARS OR AT THE TIME OF POSSESION,BT NOW THEY ARE FORCING BUYERS TO TAKE LOAN (THIS MEANS BUYER HAS TO PAY 25% OWN CONTRIBUTION TO BUILDER AND BANK WILL PAY LOAN AMT,WHICH IS TOTALLY AGAINST THEIR PROMISE WHICH THEY HAD GIVEN AT THE TIME OF LAUNCHING THIS SCHEME)) NOW ,THEY SAY THEY WILL TAKE CARE OF EMI TILL 3 YEARS OR TILL POSSESSION,BUT WHY ALL THIS LOAN ,EMI ,THEY PAYING OUR EMI ? WHY AL THIS NONSENSE ? THEY PUBLISHED BIG BIG ADS IN NEWSPAPERS LIKE SAKAL AND TIMES OF INDIA FULL PAGE THAT TOO NOT SINGLE BUT 2-3 FULL PAGES FOR SEVERAL DAYS BUT NOT A SINGLE LINE THEY MENTIONED IN AD SAYING BUYER WILL HAVE TO TAKE LOAN B4 REGISTRATION ,INSTEAD ALL REST EXPENSE WHEATHER SINGLE RUPEE WAS SUPPOSED TO BE AFTER 3 YEARS OR AT THE TIME OF POSSESSION ,WHILE PAYING ONE LAKH 10-10 TIMES I AND MY FRIENDS ASKED THEM ,THAT R THEY SURE WE DNT HAVE TO PAY SINGLE RUPEE TILL 3 YEARS OR TILL POSSESSION,AND EVERY TIME THEY ASSURED US WE DNT HAVE TO PAY SINGLE RUPEE TILL 3 YEARS OR TIL POSSESSION,WE CAN UNDERSTAND NOW A DAYS BUILDERS OR COMPANIES PLAY GIMMICKS BY KEEPING HIDDEN COST BY PUTTING SMALL STAR OR HASH SYMBOL ON THEIR DECLARED ATTRACTIVE AMT,BT DIS BLDR DIDNT MENTION THAT TOO ,AND NOW DEMANDING TO PAY THEM VIA BANK LOAN,I HAVE DECIDED NOT TO PAY ,WHAT IF I FACE SAME PROB LIKE YOU,POSSESSION THEY SAY 3 YEARS,I CAN SEE ONLY BRICK WORK TILL 4 YERS AS PER YOUR PROBS,TKS FRIENDS FOR YOUR REVIEWS